Project Rakshak: road safety audits across India

Loading the map…

Crashfree India

Project Rakshak

Crashfree India

Project Rakshak

Show

Completed · 31 audited sites

Open the full report

What the audits led to

31

Sites audited

16 cities, 13 states

20

Approved or beyond

65% of sites

5

Implemented

5 stalled

Interventions costed

₹2.7–5.6 crore

Sections remember if you fold them.

31 places

Audited sites (31)

Details

Indore, Madhya Pradesh · Cohort 1

Tejaji Nagar Junction

Urban T-Intersection

High RiskIn ProgressNHAI
  1. Stage 1, In Audit, complete
  2. Stage 2, Audited, complete
  3. Stage 3, Report Submitted, complete
  4. Stage 4, Approved, complete
  5. Stage 5, In Progress, current5
  6. Stage 6, Implemented6

In Progress · stage 5 of 6

Next: Implemented

Why this location is crash-prone

4 deaths in 5 accidents. Fatal crashes in 2022, 2023, 2024 and 2025 have claimed over a dozen lives; frequent late-night crashes from overspeeding and weak enforcement.

Audit findings (5)

  • Poor junction geometry — approach sight distance severely restricted
  • No traffic control device
  • Footpaths absent on 2 of 3 approaches
  • Poor road surface causing sudden braking
  • Night lighting insufficient

Recommended interventions

  • Junction geometry improvement + visibility clearance₹5–12 lakh
  • Traffic signal installation₹5–10 lakh
  • Footpath construction on minor road approach₹3–6 lakh
  • Street lighting restoration₹1–3 lakh
  • Total₹14–31 lakh

Expected impact

30–35% crash reduction. Near-miss incidents reduce 50%+ with signal.

Who is responsible

  • NHAI / PWD (National Highway works)

    Primary

    PRIMARY — responsible authority named in the implementation status report

  • Indore Municipal Corporation (IMC)

    PRIMARY — City road junction, geometry, footpaths

  • Indore Traffic Police

    Signal installation and management

  • Additional Collector, Indore / DRSC

    Coordination

Why not yet implemented

Partially implemented. The left-hand side is being upgraded to a 4-lane highway with safety measures at the work zone; bridge street lighting works; rumble strips and sign boards are in place. The right-hand side falls under Indore Municipal Corporation.

Progress record

  1. In Progress

    11 Nov 2026

    LHS 4-lane upgrade under way; lighting, rumble strips and signs in place. RHS is IMC's jurisdiction. (Implementation status report, Cohort 1.)

Photos and videos

Audited by

Visioneers