What the audits led to

31

Sites audited

16 cities, 13 states

20

Approved or beyond

65% of sites

5

Implemented

5 stalled

Interventions costed

₹2.7–5.6 crore

Cohort by cohort

Sections remember if you fold them.

133 places

Audited sites (31)

Team blackspots (102)

Details

Vijayawada, Andhra Pradesh · Cohort 1

NH-65 Rythu Bazar, Krishnalanka

NH Junction at Market Zone

Medium RiskApprovedNHAI
  1. Stage 1, In Audit, complete
  2. Stage 2, Audited, complete
  3. Stage 3, Report Submitted, complete
  4. Stage 4, Approved, current4
  5. Stage 5, In Progress5
  6. Stage 6, Implemented6

Approved · stage 4 of 6

Next: In Progress

Why this location is crash-prone

Market zone on NH-65. 3 accidents including 1 fatality in 2023.

Audit findings (4)

  • NH speed not reduced approaching market zone
  • No pedestrian crossings on NH at Rythu Bazar access
  • Market vehicles parked on NH shoulder blocking sight distance
  • Road markings absent

Recommended interventions

  • Speed calming: warning signage + rumble strips₹2–5 lakh
  • Pedestrian crossings with road studs on NH₹3–6 lakh
  • No-parking enforcement on NH shoulder₹1–2 lakh
  • LED lighting at market zone crossing₹2–4 lakh
  • Total₹8–17 lakh

Expected impact

25–30% crash reduction. Pedestrian fatality risk reduced ~40%.

Who is responsible

  • NHAI (PIU, Vijayawada)

    Primary

    PRIMARY — NH-65 structural and geometric works

  • AP R&B Department

    Technical coordination with NHAI

  • VMC

    Local approach roads

  • DC Krishna / DRSC

    Coordination

Why not yet implemented

In-principle approval from AP R&B NH Division. Coordination with NHAI PIU in progress.